ASNZS 4801 AS-ISO 9001
Home > Project History > SA Government Adelaide CBD rollout 

 

Head Office

8-16 Second Avenue,
Payneham South 5070,
South Australia

Telephone

61 8 8333 7200

Facsimilie

61 8 8333 1338

Mobile/Cellular

0417 393 260 - Michael DeVizio

e-mail
enquiries@sadirectional.com.au

 

South East Water Pressure Sewer System - Cannons Creek

When:

October 2004

Client:

South East Water, Victoria

 

Scope of Work:

SADB was awarded a contract by South East Water in Victoria to install a pressure sewer system in the township of Cannon Creek. The area was serviced by a traditional septic system type sewer. This system was now aging and causing environmental damage to the local eco-environment. In particular it was leaking into the surrounding estuary. The landscape in the area is costal with shifting sands and a high water table. This area was considered to be a high risk area with the potential for huge environmental damage during construction. Initially a new gravity system was proposed for the area, however due to the flat landscape, the high water table and sandy soil conditions it was found that this traditional method would be extremely costly to install. This therefore suited a pressure sewer system, due to the construction constraints.

 

SADB were employed to install the system, an offer was made to SEW to directional drill the complete project, as it was considered that open excavation would still cause environmental damage. This offer was looked upon favourably by the client. SADB worked with the designers on redesigning sections of the project to allow for drilling. We also used our project management and civil construction expertise to ensure the client’s expectations would be met. Given an 8 week construction period, SADB completed the following activities on time and under budget. SADB employed the services of our alliance partners DCE, to take care of the customer focus and engineering issues on the project. DCE liaised with the residents, local council and SEW to ensure all the expectations of all stake holders were met. All the residents were informed through a letter drop and face to face consultation, to ensure they were aware of the works proposed for the area. This proved beneficial as there were no complaints from residents during the construction program.

 

The following Scope of Work was completed.

  1. 4000 metres of directional drilling and installation of pipe ranging from 63mm to 125mm.
  2. 160 property connections, from the newly laid mains to the house lots.
  3. 160 property boundary kits with ball valves were also installed.
  4. Installed Isolation Values, Flushing Points, Vacuum and Scour Points were installed.
  5. All fittings were fitted using an electro fusion system. Each joint was carefully welded to ensure pressure was held in the system.

 

As part of the project scope, a strict regime to test the installed system was required. The project was tested and passed with only one weld out of the 600 plus welds failing.


Most importantly the project was completed with no lost time injuries and no environmental incidents.

 

 

^ TOP

 

 

 

 

 

 
     

Site Info
 © Copyright 2004 SADB Directional Drilling

. . . . . . .